Paul
Tiña, LEED® AP, San Francisco
Associate Installation challenges The main challenges of installing a
cogen system in an existing commercial facility, according to Tiña, are
a lack of centralized plant and the issue of available physical space.
"Ideally, cogen equipment would be installed in common,’ non-tenant
areas that typically don’t generate revenue for the building owner," he
says. Bright outlook The good news, however, is that he
believes DG and cogen equipment will become more and more efficient and,
hence, operating costs per kilowatt will decrease. Twin
Tower CoGen
A Cogeneration Installation for Twin High-Rise Towers in
San Francisco Addresses Concerns About Utility Power Congestion, Rates,
Energy Savings and Paybacks
Cogeneration systems, one might argue, are on the
rise. That hypothesis, however, gains
significant credence when the nation’s largest publicly held office
building owner and manager–Equity Office Properties (EOP)–jumps on the
cogen bandwagon with a twin tower installation in San Francisco.
Further adding weight to the argument is the fact
that the office giant is embarking on a second cogen project by the
bay–a decision sure to catch the attention of other developers and
owners.
EOP’s decision to implement the technology,
according to Paulino Tiña, an associate at Glumac International, the
consulting A/E on the cogen beta project–One Market Plaza–was not that
difficult given Calfornia’s volatile energy market. In fact, he says, a
number of building owners besides EOP are considering cogen given the
urgent need to help relieve the state’s utility grid while improving
system reliability and taking advantage of alternate energy at lower
rates.
The cogen system in One Market Plaza is the first of
its kind in San Francisco. And it’s also among the first on-site power
systems to be interconnected to the San Francisco utility grid in full
compliance with Pacific Gas & Electric’s (PG&E) Rule 21
Interconnection Standards. But making the system work for the twin
high-rise office complex–Spear and Steuart Towers–took a true building
team effort that included construction manager Venture Builders and
Northern Power Systems. In contemplating cogen, the process by which
steam–in this case, for building heating–is generated from the waste
heat of engine generator cooling water and exhaust, there were a number
of obstacles, particularly those associated with trying to install
distributed generation (DG) equipment and its associated systems into an
existing high-rise building. But according to Tiña, the technology was
never really in doubt. "A review of utility trend data, billing history
and installed mechanical and electrical systems in the building clearly
indicated that the building would be an excellent choice for distributed
generation," says the engineer.
At One Market Plaza, the cogen system, which
operates in parallel with the utility, provides much of the power for
the building’s electricity demands. But to provide the greatest amount
of electrical efficiency, according to members of the Northern Power
team, the system needs to operate at near capacity. However, the waste
heat generated in this process allows the building operator to displace
the need for natural gas to fire the building’s boiler. Specifically,
the gensets offset the steam produced by the building boiler via
heat-recovery steam generators. An added benefit is that the installed
system pollutes less due to the nature and efficiency of the
reciprocating engines. Therefore, in peak heating season, according to
Northern Power, the system can provide a fuel efficiency of 78%–a number
more than twice that of the 30% figure typically delivered with grid
power. In all, the cogeneration system can deliver approximately 30% of
One Market Plaza’s yearly electricity and 85% of its yearly steam
demand, notes the on-site power specialist company.
For One Market Plaza, adjacent parking space was
procured to house said equipment. But eliminating this parking area
meant the loss of a needed revenue-generating asset for the owner. As a
result, the design team was sensitive to reduce the installation’s
impact on other revenue-generating spaces. This was no simple task as
space had to be allocated for piping, switchgear and auxiliary
equipment. Adequate space for maintenance and egress clearances also had
to be accommodated.
As far as the equipment itself, three 500 kW natural
gas-fired engine generators make up the heart of the 1.5 megawatt
system. Following a survey of the building, it was determined that a
former 1,200 sf generator room in the basement proved ideal for the new
gensets. The space would also house electrical control switchgear.
However, limited vertical space posed a problem for installation of the
corresponding heat-recovery steam generators (HRSGs). The solution,
according to Tiña, was to install the HRSGs in a 400 sf space one floor
above the genset room. A new gas meter room was also constructed
adjacent to the heat exchanger room.
To ventilate these spaces, a horizontal fresh-air
intake shaft was run along the south side of the building for combustion
air. The exhaust from the engines, says Tiña, exits the generator room
and routes to the spill-air shaft, located approximately 50 ft away, up
to and slightly past the seventh floor. The spill-air shaft also houses
an auxiliary cooling radiator and steam condenser. The three
heat-recovery steam generators and the steam generators that connect to
the building boiler system are both located in the basement.
As noted, the new DG system is paralleled with the
existing electrical distribution system in One Market Plaza and consists
of nine electrical services. Tiña says each is 4,000 amps, 480/277
volts, serviced from two separate underground utility transformer vaults
with redundant transformers connected by their secondaries. Six
services are fed from the Spear Tower vault, three services from the
Steuart Tower vault.
The Spear Street service is located approximately
250 ft from the new generator room, and the Steuart Street service is
located approximately 300 ft north of the room, one floor above. "We
performed a load profile to determine which services would best
interface with the new cogeneration plant in terms of economics and
anticipated load trend," says Tiña. Based on the study, three services
qualified, two in Spear Tower and one in Steuart.
As far as the gensets, each is connected via
additional distribution equipment to a main service entrance
switchboard. "Upon power failure, the engine generators will shut down,
since they are not able to support the total load of the two towers,"
says Tiña.
The cogen plant has been commissioned and is
operating. It’s success, Tiña hopes, will push more owners to look at
installing distributed generation in their facilities for efficiency and
reliability.
"In San Francisco, the electrical utility
infrastructure has been strained due to continued demand for more power.
And it’s been difficult due to [lack of] funding and limited space for
additional substations," says Tiña.
"As equipment becomes more efficient, more advanced
technologies, such as fuel cells, will become more attractive to
building owners," says Tiña.
In the case of One Market Plaza, the dramatically
increased fuel efficiency qualifies EOP’s new system for an incentive
rebate from the Self-Generation Incentive Program of the California
Public Utility Commission (CPUC), a program to encourage on-site
generation.
The ultimate test of the technology’s success,
however, is the fact that EOP already has plans for a cogen installation
at a second San Francisco property–201 Mission Street

![]()
Equity Office (EOP), developer of San
Francisco’s One Market Plaza, is following up its first cogen success
story in the city with plans for a turnkey, grid-connected on-site
combined heat and power (CHP) system for its 201 Mission Street office
building.
The new CHP system will meet a
significant portion of 201 Mission Street’s electricity demand and will
be fully interconnected to, and operate in parallel with, the Pacific
Gas & Electric utility’s downtown network grid. This enables the
utility grid to meet only the power needs above and beyond what the
on-site system can supply and, as a result, generated electricity
on-site will not be burdened by the losses and additional costs
associated with electricity transmission and distribution.
"The CHP system reduces the building’s
draw on the city’s overburdened power supply and further exemplifies
EOP’s commitment to making our office buildings energy efficient and
environmentally friendly," says Frank Frankini, EOP senior vice
president-engineering and energy operations. "The addition of the CHP
system furthers 201 Mission’s qualifications as a potential recipient of
the EPA’s Energy Star award for energy efficiency."
Designed to deliver improved energy
efficiency and qualify the office building for California’s
Self-Generation Incentive Rebate, the 750 kW system features two 375 kW
natural gas-fired engine generator sets that will feed two of the
building’s three electrical services. Waste heat from the engines and
exhausts will be used to produce hot water for the building’s heating
system.
Date Completed: November 12/03
Lead
Engineer: Paul Tina and Craig Corson
Glumac
Innovation: Steamheat Recovery System
Seattle
T. 206.262.1010
1325 Fourth Ave., Suite 1515
Seattle, WA 98101-2509
Portland
T. 503.227.5280
900 SW Fifth Ave., Suite 1600
Portland, OR 97204
San Francisco
T. 415.398.7667
150 California St., 3rd Floor
San Francisco, CA 94111-4525
Sacramento
T. 916.934.5103
910 Glenn Dr.
Folsom, CA 95630-2527
Irvine
T. 949.833.8190
18200 Von Karman Ave., Suite 100
Irvine, CA 92612
Los Angeles
T. 213.239.8866
617 W. 7th St., 5th Floor
Los Angeles, CA 90017-3830
Shanghai
Jing'An China Tower, Ste 303
1701 Beijing West Rd.
Shanghai 200040 China
T: (86) 21-62881010
F: (86) 21-62881050
1-888-GLUMAC-1 (1-888-458-6221) © 2010 Glumac. All rights reserved. Site design by WOW Branding.